quarta-feira, 10 de junho de 2009

terça-feira, 9 de junho de 2009

Finishing the project

Thursday (06/4th) - On this last Thursday, we had the honor to present our project to ARHTE's Banking Project Evaluator, we are so thankfull for the opportunity and all referrals to the success of the project, also to thank banks composed of teachers, PV, Sergio Brito and Luciano Borges. Means the setback of the computer is not working perfectly, we could not show the control via software, although we did a beautiful presentation, and without doubt the success came from the great effort of all staff. It was a special moment for the whole team, because as freshmen entering the Ritimo and in the spirit of ARHTE. With everything we have been very happy and pleased by the presentation of the bank examiner, who invited us with respect to present our project in Baiana Technology Fair which is scheduled to agosto/09. We have much work ahead to get some mechanical structural details in order to grow with the project. We are cheering for all of that right again, efforts are not measured in this new battle and where we can post news. Below we have the video to complete the project with a flashback from the beginning of the project, we gather all the multimedia content in this video. I hope you enjoy it.

domingo, 10 de maio de 2009

And mechanical goes on...

Saturday (05/9th) - Today in the afternoon the team made some adjustments in the second level of the arm, as structures for positioning and instação of "nylon bushings for bearing" for articulções. This week we take a considerable advance in the mechanical part of the project. We follow this Ritimo and if possible as soon as possible to expedite the completion of the mechanical. We found that although many small details are lost in a long time to resolve a few screws and nuts to finish the "nylon bushings for the joints, especially the structure of the claw with the marriage of gears and gear spacing that these should have the structure of which spans fixed. Well .. ai vai a picture of the physical part of the project, it emphasized that the 3rd level of the arm (claw) has not yet started, just cut the structures and we hurricanes to be established to 2nd level.

terça-feira, 5 de maio de 2009

Advance in the mechanical

Tuesday (05/5th) - Today we make more progress in some of the mechanical arm. Already built support for the engine continued on the structure and perform the cutting of the screw worm in the sizes needed. The arm is already assuming a similar way to the final design, as shown in new pictures posted.



domingo, 3 de maio de 2009

Mechanical ...

Saturday (05/2nd) - Today in the afternoon we meet at home to try to say that something of the mechanical part. Among some hurricanes and some of the structures we build marks the first level of the arm as well as settings for the axis of support. Still many adjustments, but this week will not be the best because of the ratings and the short time for the project. Below are some photos.

quarta-feira, 29 de abril de 2009

Mechanical definitions and project of printed circuit

Wednesday (04/29th) - Today define some things for the initiation of the mechanical part. In the base define how to position and coupling shaft that will have a crown that connected via a small strap to the engine will move the rotation axis of the base. The fact of the step motor is not mounted on top of the own axis has been discussed before, but remind that this model does not serve due to the distribution of the mass of the arm rests on the motor shaft, so to take it to center of mass that are technically Gear (crown-pinion). We took some measures regarding embuxamento of the bearings that make contact with the joints and the axle in order to avoid friction and to improve the handling of the parts already mentioned.
Also finished the first version to the printed circuit in Proteus. Although precisassemos make a double-sided card, because it would have trails going up the other one decided to simplify the design of most lines in order to do a double-sided board, but a single face. The tracks that would be passing over the other, we made a simple jumpeamento bringing to the front of the plate will be welded wire where the cable sleeve. That is simplifying the work of having to make the corrosion of other side with a very small piece of 4 channels of cable sleeve for each trio of ULN2003. Still have a tirinha cable sleeve over the plate and much better than having to print and erode both sides ...

Below is a screen print of the project in Proteus. I gave one a fairly ulhada and everything seems to be connected right. I leave here my thanks to student Bruno Cavalcanti for me oriented with the program.

sexta-feira, 24 de abril de 2009

Small progress in mechanical ...

Friday (04/24th) - Today in the afternoon we took a small shift in the mechanical part of the project. We could do some measurements to have an idea of mathematic's sketch as an area of occupancy, volume and area of operation of the prototype. We also make some appointments to implement what we had on 3D design into reality. The result was, an idea of how will be when mounted.
Yesterday we bought the tap of nylon to provide a spacer between each link and also support for the bearings of the joints. Below we have two photos of the arm resting on the floor, did not like the seams yet this was the way to "mount" to have an idea of angulation. And talking about angulation, stress the importance of a difference in angle between the basis and "penpendicular's structure" to it. Indeed we opted for an angle of this structure on the basis of 30 °, so that the total mass of the prototype to be redistributed. We believe that this angle will serve as "counter-weight" still bet on the need of using any additional weight-control if the arm tends to front (structure of the claw).